Which Austin occupancies must not share a subtotal?
Mixed-use drawings in Austin reuse the same floor plate for different mechanical systems. A residential level may be a horizontal fan-coil or a split heat pump per apartment. The retail shell under it may be an empty curb and a capped outside-air duct. The amenity deck may have a dedicated outdoor-air unit. Putting those into one “HVAC” lump hides the buyout.
Shared ventilation is the piece that gets double counted. If a rooftop energy-recovery unit feeds several floors, count the unit once and reference the riser. Do not also count it inside each tenant. Corridor makeup air follows the same rule.
Sample rows for an Austin podium building
| Row | Unit | Occupancy |
|---|---|---|
| Apartment heat pump, scheduled nominal tons | EA | Residential. Include the line-set length only if the drawings or a typical detail dimension it. |
| Retail shell curb and capped supply main | EA / LF | Shell. Tenant distribution is an alternate until a tenant plan exists. |
| Dedicated outdoor-air unit on the amenity roof | EA | Shared. One count, with the floors noted. |
| Dryer or bath exhaust riser, residential stack | LF | Keep exhaust metal and roof cap separate from supply duct. |
| Lab exhaust fan, if a lab floor is in the set | EA | Specialist. Do not price it as a toilet fan because both are exhaust. |
Energy code is a responsibility question, not a quantity
Austin projects often ask who completes energy-code documentation and duct-leakage tests. Those are not produced by measuring duct. The takeoff can list the equipment efficiency exactly as scheduled, which a code form might need, but filling the form, sealing the calculation, or certifying leakage is outside a standard estimating assignment. Say so in the proposal if the invitation to bid is vague.
Documents that change the Austin fee
Send architectural floor plans for every occupancy, the mechanical schedules, roof plan, and any tenant criteria manual. If the lab or kitchen is performance-specified rather than drawn, the quote should say the quantities stop where the drawings stop. A priced estimate still needs your equipment quotes. The estimating fee is for the desk work, not the installed cost of the building.