Why Phoenix roof plans need their own subtotal
In Phoenix the roof is the mechanical room. Packaged units sit in rows, supply and return ducts run across the roof, and then drop into the building. Interior plans show the drops and the diffusers. If you measure only the reflected ceiling plan, you miss the roof duct. If you measure only the roof, you miss the drops and the terminals.
Insulation is the specification that changes the price of that roof duct. Exterior duct wrap, thickness, and weather jacketing are not the same product as interior liner. Give them different rows and different units. Square feet of wrap and linear feet of duct are both legitimate, but the proposal must say which one you will deliver.
Sample Phoenix rows
| Item | Unit | Roof or interior |
|---|---|---|
| RTU, scheduled cooling tons and heat type | EA | Roof equipment. One curb per unit unless a common curb is drawn. |
| Exterior supply duct on the roof | LF and insulation SF, both labeled | Roof. Jacketing called out from the spec section. |
| Interior drop and branch | LF | Interior. |
| Diffuser or troffer, neck size | EA | Interior ceiling. |
| Makeup-air unit at a kitchen or warehouse door | EA | Its own system, not part of the office RTU count. |
Do not resize the unit
A common request is to “add capacity for Phoenix.” That is a design change. The estimating desk counts the unit on the schedule. If the schedule is blank, the equipment is an allowance with the allowance named, or it is excluded. A separate load-calculation quote can be requested; it is not included in a quantity takeoff.
Large roofs also create labor assumptions: distance from the crane pad, screen walls, and night sets. Those affect hours, not the number of curbs. Send the labor rate and say whether one crane mobilization covers the whole roof.
Package to send
Send the roof plan, mechanical floor plans, equipment schedule, insulation specification, and any kitchen or process drawings. Name the building. A campus with three roofs is three roof subtotals unless you want one combined bid with the buildings identified.