What is actually new on a New York floor?
Existing buildings show a lot of pipe and duct that the contractor will not buy. Screen the demolition plan against the new-work plan. New branch duct from an existing shaft tap is new sheet metal. The shaft that already runs to the roof is existing unless a riser-replacement drawing says otherwise. The same rule applies to steam or hydronic mains in the ceiling of the floor below.
Terminals tell the story of the floor. Chilled beams, fan-powered boxes, or a dedicated outside-air system each have their own schedule. Count them from the schedule and prove each tag on the plan. A tag that appears on both a demo plan and a new plan needs a note: removed, relocated, or new.
Sample rows for a phased Manhattan floor
| Item | Unit | Base or alternate |
|---|---|---|
| New medium-pressure duct on the current floor | LF or LB, stated | Base, this phase only. |
| Connection to existing riser, with valve if drawn | EA | Base. Not the full riser length. |
| Fan-powered box, tag FPB-12 | EA | Base if the schedule says new. |
| Future-phase diffusers on a grayed plan | EA | Alternate. |
| Rigging / after-hours delivery | allowance or exclude | Cost note. Not a measured quantity. |
Hoisting, nights, and protection
A unit that cannot use the freight elevator changes the price and not the count. Write “delivery method unresolved” unless the logistics plan is in the documents. Night work and floor protection are labor and general-condition items. Include them only with an hour or shift allowance the contractor agrees, or exclude them.
Landlord criteria often assign the base-building air handler to someone else and leave the tenant with downstream duct and boxes. Read that criteria manual before measuring the roof. If it is missing, the roof equipment is an open item, not a guessed rooftop unit.
Documents
Send the tenant plans, landlord criteria, demolition plans, riser diagrams for the shafts you may tap, and the bid form that says who carries controls and air balance. Name the floor and the phase. A zip file of every floor in the building without a phase label will be quoted as a larger review.