Why a Chicago riser diagram controls the pipe total
Floor plans show the branches. The riser diagram shows the vertical pipe that repeats through the shaft. Measure the riser from the diagram, using floor-to-floor height from the architectural sections when the mechanical sheet does not dimension it. If the height is missing, the riser length is an open item, not a guessed 12 feet.
Heating and cooling water share shafts and must not share a total. A 4-inch heating-water riser and a 4-inch chilled-water riser are two lengths, two insulation specs, and often two jacketing specs. Steam, when the building still has it, adds traps, drip legs and a different specification again.
Sample Chicago shaft rows
| Riser or plant item | Unit | Source to cite |
|---|---|---|
| Heating-water riser, 4 inch, floors 3–18 | LF | Riser diagram plus floor-to-floor height. |
| Chilled-water riser, 6 inch, same floors | LF | Separate insulation thickness from the heating riser. |
| Floor takeoff fitting and shutoff valve | EA | One per floor that the plan shows a branch, not one per floor automatically. |
| Rooftop air handler with preheat coil | EA | Preheat is a coil and a piping connection, not part of the fan count. |
| Heat trace on exposed cooling-coil piping, if specified | LF | Quote the specified wattage and the linear feet drawn, or exclude it. |
Heating plant versus tenant floors
A downtown bid may include the basement boilers or only the tenant floor. Read the invitation. Boiler, pumps, breeching and flue are a plant package. A tenant fit-out that taps an existing riser is a valve, a coil and downstream duct. Bidding the boiler into a one-floor office fit-out is a scope error.
Winter work changes labor and temporary heat, which are cost items. The quantities of pipe and duct do not grow because the bid is in January. State temporary heat as included with a defined allowance or excluded.
What the Chicago package should contain
Send architectural sections (for floor height), mechanical risers, typical floor plans, equipment schedules, and the specification sections for hydronic piping, insulation and boilers. Identify whether steam is in this contract. If you want pricing, send dated equipment quotes and the labor rate that applies to this job, including any project labor agreement that is actually attached.