What belongs in a Houston central-plant takeoff?
A Houston mechanical bid often has two different jobs on one set of drawings: the plant that makes chilled water, and the distribution that delivers air and water to the floors. Price them as separate assemblies. The chiller, cooling tower, pumps and chemical treatment sit on an equipment schedule. The chilled-water and condenser-water mains, valves, specialties and insulation sit on the riser and plan drawings. Neither total replaces the other.
Occupied healthcare work needs a third split. Comfort air for offices and lobbies is not the same system as isolation exhaust, operating-room air changes, or a laboratory hood. If the sheets do not name the service on the duct, stop and list the run as unresolved instead of calling it supply air.
Sample line items for a Houston plant and distribution bid
These rows show how a schedule should read. They are a format example, not a Houston price and not a completed project.
| Item | Unit | Why it is its own row |
|---|---|---|
| Water-cooled chiller, tag CH-2 | EA | Match the schedule tonnage, voltage and starter. Do not infer capacity from a floor-area rule. |
| Cooling tower, tag CT-1, with basin heaters if specified | EA | Basin heat, vibration isolation and access ladders are accessories, not part of the tower count. |
| Condenser-water pipe, 8 inch | LF | Keep pipe length separate from grooved couplings, valves and hangers. |
| Isolation exhaust duct, welded stainless if specified | LF | A process or medical material spec cannot be measured as galvanized comfort duct. |
| Outdoor-air handler with reheat coil | EA | Humidity control is an equipment row plus the coil connection, not a percentage of cooling tons. |
How Houston drawings usually fail a bid review
Plant rooms are revised by addendum while the floor plans stay on an older issue. Record both issue dates. A new chiller selection can change nozzle sizes, primary pipe, electrical connection and concrete housekeeping pads. Those changes belong in a revision column, not folded into the original quantities.
Roof equipment also needs a responsibility check. Screen walls, structural curbs, lightning protection and roofing patches are often outside the mechanical contract even when the unit is shown on the mechanical roof plan. List them as exclusions unless the specifications assign them to Division 23.
What to send for a Houston quote
Send the equipment schedules, riser diagrams, enlarged plant plans, air-balance diagrams if you have them, and the specification sections for chillers, towers, duct and insulation. Name the job address and whether the building will stay occupied. Say if you want quantities only or a priced estimate that uses your supplier quotes and labor rates. Freight to a Houston dock, crane time and temporary cooling are allowances until those quotes exist.