What does altitude change in a Denver takeoff?
It changes the note you write beside the equipment, not the arithmetic of the count. Manufacturers derate cooling equipment at elevation. If the schedule lists a model and a capacity, that is the row. If a contractor asks to “add tons for Denver,” the correct response is to request a revised schedule or a separate load calculation. Inventing capacity is design.
Heating is easy to undercount because the cooling conversation is louder. Look for boilers, pumps, hot-water coils, electric duct heaters, or gas heat in packaged units. A building can have all of those in different zones. Each gets a row.
Sample Denver rows
| Item | Unit | Altitude or winter note |
|---|---|---|
| Air handler, scheduled CFM and model | EA | Do not substitute a sea-level equivalent model. |
| Condensing boiler, tag B-1 | EA | Include the scheduled vent material as its own row if specified. |
| Heating-water pipe, by size | LF | Separate from chilled water. |
| Roof duct with specified insulation | LF | Snow guards or equipment screens only if detailed. |
| Heat trace, exposed piping, if specified | LF | Excluded when the spec does not call for it. |
Roof access is a labor assumption
Setting units on a Denver roof in winter can limit crane days and add protection of the membrane. That belongs in the labor narrative and the exclusions. The number of curbs is still the number of curbs drawn. If the structural plans show a different curb opening than the mechanical plans, log the conflict before anyone buys a curb.
Hydronic specialties matter in this climate: air separators, expansion tanks, and glycol fill if specified. Count them from the diagram. Glycol is a material allowance with a concentration only when the spec states one.