Where do Las Vegas hotel quantities get blended by mistake?
The tower is repetitive. A typical guest-room plan can be counted by room type if the drawings give a matrix. The podium is not repetitive. A restaurant, a show kitchen, a ballroom and a casino floor each have air handlers, exhaust and sometimes smoke control that the guest-room typical does not contain. Blending them produces a number that purchasing cannot buy against.
The pairing rule in the podium is exhaust plus makeup. A type I hood without a makeup unit is an incomplete system. If the architectural kitchen set shows the hood and the mechanical set does not show makeup, log the gap. Do not invent a unit size.
Sample Las Vegas rows
| Package | Unit | Repeat rule |
|---|---|---|
| Guest-room fan-coil or PTAC, room type K | EA | Count from the room matrix, not from one enlarged plan. |
| Corridor dedicated outdoor-air unit, tower | EA | One per the schedule, serving the floors listed. |
| Ballroom air handler | EA | Podium. Not a multiple of the guest-room unit. |
| Type I hood exhaust fan and duct | EA / LF | Kitchen. Material and weld spec as written. |
| Makeup-air unit for that hood | EA | Pair to the hood. Scheduled CFM only. |
Smoke control and special systems
Some assembly spaces include smoke exhaust or stair pressurization. Those fans and ducts are life-safety systems. Keep them out of the comfort-air pound total and out of the kitchen total. If your contract does not include them, exclude them by specification section.
Pool and spa dehumidifiers, where the amenity drawings show them, are high-latent units with special duct material. They are not guest-room fan-coils.
Cooling capacity stays on the schedule. A request to add tons for the desert is a redesign, not a takeoff revision.
What to send
Tower typicals, the room matrix, podium plans, kitchen equipment plans, and schedules for both tower and podium. Name the phase if the podium opens before the tower. Send labor rates and equipment quotes if you want a priced estimate rather than quantities. Crane and swing-stage assumptions for a tower roof should be stated by you or excluded.